Question 1
When is implementation of a Product Backlog item considered complete? (Choose the best answer)
  1. At the end of the Sprint.
  2. When the item has no work remaining in order to be potentially released.
  3. When QA reports that the item passes all acceptance criteria.
  4. When all work in the Sprint Backlog related to the item is finished.
Correct answer: B
Question 2
Choose two responsibilities of a self-organizing Development Team. (Choose the best two answers.)
  1. Reorder the Product Backlog.
  2. Pull Product Backlog items for the Sprint.
  3. Do the work planned in the Sprint Backlog.
  4. Increase velocity.
  5. Report daily progress to stakeholders.
Correct answer: BC
Question 3
Every Development Team should have: (Choose the best answer.)
  1. At least one representative from each major software engineering discipline (like QA, Dev, UX).
  2. The competencies and skills needed to deliver a Done Increment in a Sprint.
  3. One Lead Developer and no more than 8 other members.
Correct answer: B
EXAM SIMULATOR

How to Open TQB Files?

Use Taurus Exam Simulator to open TQB files

Taurus Exam Simulator


Taurus Exam Simulator for Windows/macOS/Linus

Download

Taurus Exam Studio
Enjoy a 20% discount on Taurus Exam Studio!

You now have the chance to acquire Exam Studio at a discounted rate of 20%.

Get Now!
-->